The 6 Brindabella Circuit project is advancing well with notable progress being made on al fronts including curtain wall & fins, skylights, core cladding, canopy structural steel and partitions and ceilings.  The external landscaping work have also commenced with site preparation, expansion of the site area to allow integration of the 6 Brindabella landscaping into the town square and main spine walkway.

Internal finishes are well underway with bathrooms being fitted off, carpet being installed, lift shaft structural steel finished and services such as light fittings being fitted off.  The project is due for Practical Completion by June 2022.


Plaza Canopy installation – Western Elevation


Plaza Canopy roof installation


Skylight


Southern Building – Atrium lift structural steel


Carpet Installation – Southern Building, Level 1